Work on the Imps Territory development at the ProAmpac Stadium has continued at pace throughout the summer, with significant progress being made across the club’s new hospitality facilities and wider stadium infrastructure as the project heads into the final weeks.
The transformation of the new hospitality space has reached another important milestone, with the installation of the external glazing now complete. Inside, plastering has been finished, while the mechanical and electrical infrastructure is entering its final stages.
Accessibility has also been enhanced with the installation of the new passenger lift up to the new hospitality area - this will be accessed via the eastern end of the building.
The new air handling system, which will provide air conditioning throughout the facility, has also been installed.
The bar area is now ready for its fit-out, with the walls, panels and pipework all in place ahead of the installation of worktops. Preparation work has also been completed in the kitchen area, with the main kitchen installation set to begin this week.
Plumbing work for the new toilet facilities is now largely complete, while extensive data cabling for the stadium’s new LED advertising boards, media systems and big screen is also approaching completion.
Elsewhere around the stadium, surfacing works within the bowl are in their final stages, while seating is now being installed in the Stacey West Stand as part of the wider improvements.
The club’s sustainability programme has also taken another step forward. Solar panels installed on the roof of the Greenlinc Renewables Stand are currently undergoing testing, with additional panels being installed on the roof of the Rilmac Stand.
The extensive redevelopment is continuing throughout the close season as preparations continue ahead of the 2026/27 Sky Bet Championship campaign.